Map for the production of concrete mixes. Technological process of preparation of concrete mixtures. Scope of antifreeze additives


TYPICAL TECHNOLOGICAL CHART (TTK)

INSTALLATION OF CONCRETE PLANT SB-75

1 AREA OF USE

Typical routing designed for the installation of a concrete plant SB-75.

Composition and classification of concrete plants and concrete mixing plants

Types, composition and performance of concrete plants and concrete mixing plants. A concrete plant is a production plant for the preparation of concrete mixtures. According to their purpose and conditions for the consumption of concrete mixtures, concrete plants are: central district (CBZ) - to provide concrete for objects in a certain area located at distances from the CBZ that allow transporting concrete mixtures without deteriorating their quality (up to 50 km); they are calculated for a long period of work (more than 5 years); near-object - for servicing objects either significantly remote from the CBZ, or not connected with it by roads. Concrete mixtures in small volumes can be prepared using concrete mixing plants (BSU) mounted near the place of consumption of concrete. Plants and polygons of prefabricated reinforced concrete have, as a rule, their own concrete mixing shops.

Concrete plants and installations are stationary and mobile, the latter include floating concrete plants. Mobile concrete plants can reduce the distance and duration of transportation of the concrete mixture.

The composition of the concrete plant (Fig. 1) includes: concrete mixing plant (workshop); warehouses of aggregates with devices for their heating in winter period; cement warehouse; devices for unloading and transporting components; compressor room; boiler room, utility rooms; individual plants have workshops for the preparation and enrichment of aggregates.


Fig.1. Master plan of the automated concrete plant:
1 - control panel for aggregate warehouse; 2 - device for unloading crushed stone; 3 - inclined overpass; 4 - railroad cement warehouse;
5 - compartments for storage of aggregates by types and fractions; 6 - radial stacking conveyor; 7 - stacked transport galleries; 8 - knot of an overload of fillers; 9 - drying department; 10 - inclined gallery; 11 - conveyors for supplying sand for drying;
12 - dosing department; 13 - capacity for cement; 14 - concrete mixing plant; 15 - compressor; 16 - transformer substation; 17 - heat point

The main technological feature of the BSU classification is the nature of their work - cyclic or continuous. In accordance with this, BSUs of cyclic and continuous action are distinguished, differing in the device of batchers and concrete mixers. Technological equipment of a concrete plant is selected according to the performance of the leading machine - a concrete mixer.

The performance of continuous concrete mixers is indicated in their passports.

Layout of concrete mixing plants. The layout of the equipment of concrete mixing plants (Fig. 2) is single-stage (vertical) and two-stage (parterre type). A single-stage BSU has a significant height (16-20 m) and small dimensions in plan; a two-stage batching plant, on the contrary, has a small height, and its dimensions in terms of are significant. The industry produces unified one-, two- and three-section batching plants (both vertical and parterre type), in each section there are two or three concrete mixers. The mixing plant of a concrete plant includes such a number of BSU sections that corresponds to the required capacity of the plant.

Fig.2. Layout diagrams of concrete mixing plants:
but- single-stage (vertical); b- two-stage (parterre): 1,2 - conveyors for the supply of aggregates; 3, 9, 10 - rotary guides and funnels; 4 - account bunkers; 5 - cement pneumatic supply pipe; 6, 7, 8 - dispensers of cement, aggregates and water;
11 - mixers; 12 - distributing bunker (hoarder); 13, 14 - concrete truck; autocementosis; 15 - skip hoist

In the Russian Federation and in many other countries, batch batching plants are more widely used, which is explained by the periodic nature of the consumption of the concrete mixture. Continuous batching plants have significant batching errors, difficulty in operating batchers that are complex in design, and the presence of a non-discharging residue of the concrete mixture at the bottom of the concrete mixer.

By the nature of the process control, BSU (and, accordingly, plants) can have local, remote, automated and automatic control. At local government dispensers have manual shutters, and electric motors are equipped with individual starting equipment. Remote controlled batching stations have one or more control panels for turning on, off and stopping individual or interlocked mechanisms. Automated BSUs also have remote control of the operation of mechanisms; in addition, they are equipped with automatic controllers for all technological processes. With the program control of an automated BSU, the regulators operate without human intervention, therefore, for the operation of the BSU, only operators on the control panel and mechanics on duty are needed. The highest level of automation is the automatic control of the BSU operation, which includes program control by setting concrete grades, automatic introduction of corrections for the moisture content of aggregates, registration of the specified and actual mixture composition.


Each concrete mixing plant is a set of technological equipment for receiving and dosing components, preparing and dispensing the finished mixture. In the technological schemes of BSU, three main technological lines can be distinguished: the supply of aggregates, the supply of cement, and the preparation of concrete mix. A single-stage single-section concrete mixing plant (Fig. 3) is designed to prepare a concrete mixture on dense and porous aggregates.

Fig.3. Single-section concrete mixing plant SB-6:
1 - water dispenser; 2 - receiving funnel: 3 - concrete mixer; 4 - distributing bunker; 5 - elevator; 6 - cement dispenser; 7 - filler dispenser; 8 - transition pipes; 9 - sand breaker; 10 - metal carcass; 11 - rotary funnel; 12 - belt conveyor; 13 - bunker

It is a four-tier structure with a metal frame and an inclined gallery adjacent to it, in which a belt conveyor is placed for supplying aggregates to the fourth tier - to the over-bunker compartment; cement is supplied here by a vertical elevator. On the third and second tiers, respectively, supply bins of components with dosing gates and two gravity mixers of cyclic action are placed.

Two-section single-stage batching plants with gravity or forced mixing mixers with a capacity of 330 to 1600 liters have a similar equipment layout.

Fig.4. Continuous concrete mixing plant SB-75:
but- technology system; b - general form: 1 - batchers of aggregates; 2 - lower assembly belt conveyor; 3 - inclined belt conveyor; 4 - expendable bunkers of aggregates; 5 - supply hopper of cement; 6 - filter; 7 - supply tank of water; 8 - cement dispenser; 9, 10 - three-way valves; 11 - sleeve for water drainage; 12 - dosing pump; 13 - concrete mixer; 14 - storage bunker; 15 - calibration batcher of cyclic action; 16 - truck mixer; 17, 18 - lower and upper two-arm funnels

Continuous concrete mixing plant has a two-stage equipment layout, (Fig. 4); it consists of dosing and mixing departments, cement supply hopper, inclined belt conveyor and control unit. A storage hopper is used to dispense ready-mixed concrete. 14; the delivery of dry mix to truck mixers is provided by two two-arm funnels 17, 18. There is a control batcher of cyclic action 15 - for calibration of working batchers of continuous action 1, 8. To provide concrete mix for high-speed road construction, automated concrete mixing plants with a capacity of up to 120 m/h have been created, having a similar layout. Block design of installations with two-stage scheme expands the scope of their application: they can be used as stationary and as temporary, easily relocated to a new site.

Types of concrete mix and the composition of the processes in its preparation

The composition of the concrete mixture, as well as the technology of its preparation, determine the type and operational properties concretes, which according to their purpose are divided into general construction, hydraulic engineering, road, decorative, heat- and corrosion-resistant, as well as concretes for special construction. Many features of the classification of concrete mixtures coincide with the features of the classification of concrete. However, there are also specific features. Concrete mixtures are classified according to their consistency, which is the main technological characteristic mixtures. According to the consistency, the workability of concrete mixtures is evaluated and they are divided into rigid and mobile. For example, mobile mixtures are divided into slow-moving (draft 0-3 cm), moderately mobile (4-7 cm), mobile (8-15 cm) and cast (16 cm or more) in terms of mobility - the draft of a standard cone. When assigning the consistency of a concrete mixture, the following should be taken into account: rigid mixtures do not require large amounts of cement, provide high density concrete, are not subject to delamination, reduce the time of curing concrete, they are most applicable for concreting massive structures; mobile mixtures are workable, their use leads to a reduction in labor costs for concrete work, as well as to an increase in the quality of concrete in thin-walled densely reinforced structures.

I. SCOPE

The technological map is developed on the basis of the methods of scientific organization of labor and is intendedfor use in the development of a project for the production of work and the organization of labor at mixing plants for the preparation of cement concrete mixtures.

The following basic conditions are accepted in the map.

The automated plant with a mixing plant SB-78 operates in the general complex of machines and mechanisms forabout the device of cement-concrete pavements of highways.

Consumable storage of sand and graded crushed stone open type with dividing walls is located next to the mixing plants. Hand the stock of materials must be created in the warehouse, sufficient for the operation of the installations for 10 days. Sand and fractionated crushed stone are delivered to the supply warehouse in railway cars or by road. In the case of delivery of unfractionated or contaminated crushed stone, washing and sorting of the material into fractions should be organized. Sand and crushed stone are fed into the feeders of the batching department by bucket loaders of the TO-18 or "Case" type.

The mixing plant is supplied with cement from a consumable warehouse with a capacity of 300 tons.

Cement is delivered to the consumable warehouse by cement trucks.

The site of the plant has a hard surface, drainage is provided. The territory of the plant is fenced with a temporary fence. To the plant underprovided water and electricity.

A hard-surfaced access road has been laid to the mixing plant. The movement of cars is organized according to the ring scheme without oncoming traffic.

For the export of cementa column of dump trucks with an estimated number of vehicles is fixed to the concrete mixture.

The number of vehicles is adjusted depending on the distance of transportation of the mixture and road conditions.

In technological The map provides for a plant capacity of 320 m 3 per shift.

When changing the conditions accepted in the technological map, it is necessary whenknitting it to new conditions.

. MANUFACTURING PROCESS INSTRUCTIONS

Automated cementobeton plant (TsBZ) with the SB-78 plant is designed for the preparation of rigid and plastic concrete mixtures with aggregate fraction sizes up to 40 mm .

Technical specifications

Prod driving, m 3 / h ............................................... ........ 60

Fra quantity pieces of aggregates:

sand................................................. .......................... one

rubble n................................................. ......................... 3

The largest th placeholder size, mm................................... 70

Feed hopper capacity, m 3

filled threads ................................................. ............ 36

cement but................................................. ...................... 12

Mouth new power, kW ............................................... 57,8

Dimension dimensions, mm:

dl ina ................................................. ......................... 36800

width................................................. ....................... 2600

height................................................. ......................... 12520

Weight, T....................................................................................... 3

Installation and consists of the following main blocks (see figure):

continuous concrete mixer, the working body of which is square-section shafts with cast blades made of steel 35 GL mounted on them. work surfaces lothe mouths are located at an angle of 45° relative to the axis of the shaft;

supply hopper of cement, which is a cylindricala conical container and a dispenser designed to receive cement and feed it with cement. The bunker is equipped with a filter for cleaning the exhaust air before it is released into the atmosphere and automatic indicators of the lower and upper levels;

dosing unit, consisting of four consumable buanchors for crushed stone and sand with dispensers. A B-21 vibrator is fixed on the inclined wall of the sand bin. The batchers are mounted above the horizontal collection conveyor, which transports the materials to the inclined conveyor and then to the concrete mixer.

Technological scheme of work of the pulp and paper mill with mixer SB-78:

Notes. one . The numbers above the line are the duration of operations in minutes.

Description of works

The composition of the link (team)

unit of measurement

Scope of work

Norm of time

Price, rub.-kop.

Standard time for the entire scope of work,people-h

The cost of labor costs for the entire scope of work, rub.-cop.

Local norm SU-921 of the trust "Dondorstroy"

Checking SB-78 nodes before starting work. Ce dispenser settingment and checking the operation of all dispensers. Checking the operation of nodes idle. Checking the quality of produced concrete and adjusting the supply of water and cement. Preparation and production of ready-mixed concrete in automatic mode. Tidying up workplaces and mixing plant at the end of the shift. Plant maintenance, monitoring technical condition power equipment

Mixing plant operator 6 years - one

Assistant driver (construction locksmith) 4 times. - one

Front loader driver "Case" 6 years. - 1

Cement supply fitter 4 size. - one

Road worker servicing dispensers inert materials 3 bit. - 1

Electrician 5th category - one

100 m 3

15,6

10-62

99,84

67-97

Total: 640 m 3

99,84

67-97

per 100 m 3

15,6

10-62

. TECHNICAL AND ECONOMIC INDICATORS

unit of measurement

According to calculation A

Schedule B

How much % is the indicator according to the graph more (+) or less (-) than according to the calculation

work hard bone works at 100 m 3 mixtures

people-h

15,6

Average rank of workers

Average week nevnaya wage one worker

rub.-kop

  • 7. Productivity of transport of cyclical action, the method of its calculation. Soil transportation by cyclic transport
  • 8. Methods for the production of earthworks and the conditions for their use.
  • 9. Technology of soil development by excavators with working equipment "dragline"
  • 10. Technology of soil development by excavators with working equipment "straight shovel"
  • 11. Technology of soil development with working equipment "backhoe"
  • 12. The performance of single-bucket excavators, the method of its calculation and ways to improve it
  • 13. Technology of soil development by bulldozers. Development methods, schemes of working movements and their characteristics
  • 14. The performance of bulldozers, the method of its calculation
  • 15. Technology of soil development with scrapers. Methods of development, schemes of working movements and their characteristics.
  • 17. Factors affecting the intensity of soil compaction and their characteristics
  • 18. Methods of soil compaction, their characteristics and conditions of use
  • 19. Technology of soil compaction by machines of static and dynamic action
  • 21. Technological features of soil development in winter
  • 22. Technology for the preparation of concrete mix
  • 23. Technology of laying concrete mix in concreting blocks.
  • 26. Defects in concrete masonry and ways to eliminate it. Concrete care
  • 27. Quality control of concrete works
  • 28. Pile driving technology
  • 29. Stuffed pile technology
  • 30. Acceptance of pile work. Quality control
  • 31. Basic technological schemes for the installation of reinforced concrete structures
  • 32. Scope of work for the installation of welded structures at the construction site
  • 33. Features of the installation of reinforced concrete structures in winter conditions
  • 36. Masonry production technology
  • 36. Features of stone work in winter
  • 37. Purpose and types of waterproofing works (gir)
  • 38. Technology for the production of waterproofing works
  • 39. Technology of production of thermal insulation works.
  • 40. Features of the production of weights in winter conditions
  • 41. Features of the thermal insulation device in winter conditions.
  • 42. Types of roofs and roofing technology
  • 43. Features of work on the installation of the roof in winter conditions
  • 44. Technology of preparing surfaces for plastering and plastering surfaces
  • 45. Features of the production of plaster work in winter conditions
  • 46. ​​Production of works on facing buildings with various materials
  • 47. Features of the production of facing works in winter conditions
  • 48. Surface preparation, application and processing of prepared layers for painting
  • 49. Painting of internal and external surfaces of structures
  • 50. Technology of pasting surfaces with wallpaper
  • 51. Painting and wallpaper work performed in winter conditions
  • 52. Technology of flooring from various materials
  • 53. Construction technology of subgrade and pavement (improved capital and transitional types)
  • 54. Pavements with transitional types of pavement.
  • 55. Improved types of pavement.
  • 56. Quality control in road construction
  • 57. General provisions for the reconstruction of buildings and structures.
  • 58. Dismantling and liquidation of buildings and structures
  • 59. Concrete and reinforced concrete works
  • 60. Dismantling of building structures. Strengthening building structures
  • 22. Technology for the preparation of concrete mix

    The technological process of concreting structures includes the preparation of the concrete mixture and its transportation to the facility under construction, its supply, distribution, placement and compaction in the structure, the care of concrete during the hardening process.

    Concrete mixture cannot be prepared in advance and transported to long distances. After preparation, it must be delivered and placed in the blocks of the structure before setting begins (usually 1 ... 3 hours). Therefore, the concrete mixture must be prepared near the places of its laying so that the time it takes to travel in the summer does not exceed 1 hour.

    The concrete mixture is prepared on a mechanized or automated concrete plant in ready-made delivered to the construction site or prepared on-site inventory (mobile) concrete mixing plants.

    Preparation of concrete mix consists of the following operations: reception and storage of constituent materials (cement, aggregates), weighing (dosing) and mixing them with water and issuing the finished concrete mixture to vehicles. IN winter conditions This technological process includes additional operations.

    The concrete mixture is prepared according to the finished or dissected technology. With the finished technology, a ready-made concrete mixture is obtained as a product, with a dissected one, dosed components or a dry concrete mixture are obtained. The main technical means for the production of concrete mix are supply hoppers with distribution devices, batchers, concrete mixers, systems of internal vehicles and communications, a dispensing hopper.

    Technological equipment of a stationary type for the preparation of a concrete mixture can be solved according to one-stage and two-stage schemes.

    A single-stage (vertical) scheme (Fig. 6.1, a) is characterized by the fact that the constituent materials of the concrete mixture (binders, aggregates, water) rise to the top point of the technological process once and then move down under the action own strength gravity during the technological process. Advantages: compact, economical, and disadvantages - the complexity of installation (due to the considerable height, up to 35 m).

    With a two-stage (parterre) scheme (Fig. 6.1, b), the rise of the constituent materials of the concrete mixture occurs twice, i.e. the components of the concrete mixture are first lifted into the feed bins, then they fall by gravity, passing through their own dispensers, fall into a common receiving funnel and rise again to be loaded into the concrete mixer. The advantage of this scheme is the lower cost of installation, and the disadvantage is a large building area.

    When the need for a concrete mix is ​​not more than 20 m 3 / h, mobile mobile concrete mixers with gravity-type mixers are usually used.

    Rice. 6.1. Layout diagrams of concrete mixing plants and installations: a - single-stage; b - two-stage; 1 - aggregate storage conveyor

    in consumable bunkers; 3, 9, 10 - rotary guide and distribution; 4 - consumable bins; 5 - cement supply pipeline; 6 - cement dispenser; 7 – filler dispenser; 8 - water dispenser; 11 - concrete mixers; 12 - distributing hopper; 13 - concrete truck; 14 - cement truck; 15 - skip hoist.

    The design of concrete mixing plants allows you to transfer from working to transport position during one work shift and transport them on a trailer to the next object. The use of such installations is expedient on large dispersed objects located from stationary concrete plants at distances exceeding technologically permissible.

    Concrete plants usually produce two types of products - dosed components and ready-mixed concrete.

    Cyclic and continuous mixers are used as equipment for the preparation of ordinary concrete mix.

    Cyclic concrete mixers differ in the volume of the finished mixture dispensed in one batch.

    The performance of the cyclic concrete mixer

    P \u003d q n k in / 1000, m 3 / h

    where q is the volume of the finished concrete mix for one batch, l; n is the number of batches per hour; k in - the coefficient of use of the concrete mixer in time (0.85 ... 0.93).

    The loading of the cyclic concrete mixer is carried out in the following sequence: first, 20 ... 30% of the amount of water required for mixing is supplied to the mixer, then cement and aggregates are simultaneously loaded, without stopping the water supply to the required amount. The cement enters the mixer between the batches of aggregate, thereby eliminating its spraying. The duration of mixing the concrete mixture depends on the capacity of the mixer drum and the required mobility of the concrete mixture and ranges from 45 to 240 s.

    Continuous concrete mixers are produced with a capacity of 5, 15, 30 and 60 m 3 / h, and gravity-type machines with a drum mixer - with a capacity of 120 m 3 / h. The duration of mixing in these concrete mixers is indicated in the passports of the machines.

    When preparing a concrete mix using a separate technology, the following procedure must be observed: water, part of the sand, finely ground mineral filler (if used) and cement are dosed into the mixer. All these components are thoroughly mixed, the resulting mixture is fed into a concrete mixer, pre-loaded with the rest of the sand and water, coarse aggregate, and once again the whole mixture is mixed.

    The composition of the concrete mixture must provide the properties specified for it, as well as the properties of the hardened concrete.

    There are certain requirements for concrete mix:

    1) it must maintain uniformity (during transportation, reloading and laying in the formwork), which is ensured by cohesion (non-separation) and water-holding capacity. All this is achieved by the correct selection of the composition of the mixture, the accuracy of the dosage of the components and the thorough mixing of all components;

    2) be workable. Workability is the ability of a concrete mixture to spread and fill a mold under the action of vibration. It depends on grain composition mixture, the amount of water, the degree of reinforcement, methods of transportation and compaction of the mixture.

    Dry mortar(ССС) - a mixture of binder, aggregates, additives, pigments, dosed and mixed at the factory, and mixed with water before use. Accurate dosing of components allows obtaining higher technical characteristics of the finished product compared to mixtures obtained, prepared at the construction site. An important advantage of dry mixes is the possibility of adding chemical additives and microfillers to them, both improving their structure and prepared for use in the cold season.

    Concrete Mix Transportation Technology

    Transportation of concrete mix includes its delivery from the place of preparation to the construction site, the supply of the mixture directly to the place of laying, or its reloading onto other vehicles or devices, with the help of which the mixture is delivered to the concreting unit. A concreting block is a structure prepared for laying a concrete mix or a part of it with an installed formwork and mounted reinforcement.

    In practice, the process of delivering the concrete mixture to the concreting blocks is carried out according to two schemes:

    From the place of preparation to direct unloading into the concrete block;

    From the place of preparation to the place of unloading at the concrete object, with the subsequent supply of concrete to the concreting unit. This scheme provides for intermediate unloading of the concrete mix.

    Transportation and laying of the concrete mixture must be carried out by specialized means that ensure the preservation of the specified properties of the concrete mixture.

    Transportation of the concrete mix from the place of preparation to the place of unloading or directly to the concreting unit is carried out mainly by road, and transportation from the place of unloading to the concreting unit is carried out in buckets by cranes, lifts, conveyors, concrete pavers, vibratory feeders, motor carts, concrete pumps and pneumatic blowers.

    The method of transporting the concrete mixture to the place of its laying is chosen depending on the nature of the structure, the total volume of the laid concrete mixture, the daily requirement, the transportation distance and the lifting height. With any method of transportation, the mixture must be protected from atmospheric precipitation, freezing, drying, and also from the leakage of cement laitance.

    The permissible duration of transportation depends on the temperature of the mixture at the outlet of the mixer: it should not exceed 1 hour at a temperature of 20-30°C; 1.5 h - 19-10°C; 2 h - 9-5°С. Long-term transportation on bad roads leads to its delamination. Therefore, in vehicles without stirring the mixture along the way, it is not recommended to transport a distance of more than 10 km along good roads and more than 3 km - on the bad ones.

    Choice of vehicles carried out on the basis of the conditions of the facility under construction: the volume of concrete work; the period of their production; travel distances; the size of the building in plan and in height; TEP (productivity, speed of movement, unit cost of transportation). In addition, it is also necessary to take into account the requirements for maintaining the properties of the concrete mixture - preventing decay, changes in uniformity and consistency.

    To transport the mixture to the site, road transport is widely used - general-purpose dump trucks, concrete trucks and concrete mixer trucks (mixers).

    Transportation of the mixture by dump trucks. Disadvantages: there are difficulties in protecting the mixture from freezing, drying, leakage of cement milk through the cracks in the bodies, the need for manual cleaning of the body.

    Transportation of concrete mix by concrete trucks , equipped with sealed dump-shaped tipping bodies. Advantages: transportation of the mixture is possible at a distance of up to 25-30 km, and without splashing it and leaking cement laitance.

    Transportation of the mixture by truck mixers (mixers). It is the most efficient means of transportation. Concrete mixer trucks are loaded at the factory with dry components and prepare the concrete mix en route or at the construction site. The capacity of truck mixers for the finished mix is ​​from 3 to 10 m 3 . Mixing of components with water usually starts 30-40 minutes before arrival at the site. In truck mixers (mixers) it is also advantageous to transport ready-made concrete mixtures due to the possibility of inducing them along the way due to the rotation of the drum. Advantages: the range of transportation of dry mix components in truck mixers is not technologically limited.

    The concrete mixture delivered to the facility can be unloaded directly into the structure (when concreting structures located at ground level or shallow) or reloaded into intermediate containers for subsequent delivery to the concreting site.

    The mixture is fed into the structures to be concreted by cranes in fixed or rotary buckets or by belt conveyors (conveyors), concrete pumps and pneumatic blowers (through pipes), link arms and vibrating arms, belt concrete pavers. Rotary tubs with a capacity of 0.5 - 8 m 3 are loaded directly from dump trucks or concrete trucks. Belt mobile conveyors are used when it is difficult or impossible to supply the mixture to the place of laying by means of delivery or in tubs. Conveyors up to 15 m long serve the mixture to a height of up to 5.5 m. To reduce the height of free fall of the mixture during unloading, guide shields or funnels are used. Disadvantage: The conveyors need to be changed frequently during the concreting process.

    Therefore, self-propelled belt trucks are more effective in this regard. pavers mounted on the base of a tractor, equipped with a skip hoist and a belt conveyor up to 20 m long. To supply the mixture in structures located in cramped conditions and in places not accessible to other means of transport, concrete pumps. They supply the mixture through a steel detachable pipeline (concrete pipe) to a horizontal distance of up to 300 m and vertically up to 50 m. Also, for non-overload supply of the mixture and its laying, pneumatic superchargers. The maximum range of transportation by them is 200 m horizontally or up to 35 m vertically when supplying up to 20 m 3 / h. To supply and distribute the mixture directly at the installation site at a height of 2 - 10 m, apply trunks, representing a pipeline of conical metal links and an upper funnel; vibration robots, representing a link trunk with a vibrator. On the loading funnel with a capacity of 1.6 m 3 and sections of the vibro-shoe with a diameter of 350 mm, vibrators-stimulators, as well as dampers, are installed every 4-8 m.

    The supply and distribution of the concrete mixture in the structure at a distance of up to 20 m with a slope of 5-20 ° to the horizon is ensured by vibration chutes in conjunction with vibration feeder with a capacity of 1.6 m 3. They can lay mixtures up to 5 m 3 /h at an angle of inclination of 5 °, and at an angle of 15 ° - up to 43 m 3 / h.

    I approve:

    ______________________

    ______________________

    ______________________

    "____" __________ 200 g.

    ROUTING

    TECHNOLOGICAL CARD FOR CONCRETING STRUCTURES

    REINFORCING, FORMWORKING AND CONCRETE WORKS

    No. p.p.

    Page number

    Title page

    General provisions

    Requirements for concrete and concrete mix

    Technological tooling and equipment

    Preparatory, formwork and reinforcement works

    concreting

    curing concrete

    Quality control of work

    Labor protection in the production of works

    environmental protection

    Bibliography

    3.2. Regardless of the time of year, due attention should be paid to complex moisture and heat protection equipment, which should ensure the acceleration of concrete hardening under conditions of curing in the formwork or under a heat and moisture protective coating, and at the stage of heating and cooling of concrete, exclude the possibility of thermal cracks.

    3.3 Integrated moisture and heat protection equipment consists of:

    Inventory metal formwork with a forming surface;

    Moisture and heat-protective inventory coatings - to protect unformed surfaces of freshly laid concrete from moisture and heat exchange with the environment;

    Awning to protect the concrete surface from rain during work in rainy weather;

    Enclosing greenhouses-shells with load-bearing frame And necessary quantity heat generators (when performing work in the winter season).

    3.4. Polymer films (polyethylene, polyvinyl chloride, etc.) with a thickness of at least 100 microns or rubberized fabric can be used as moisture-proof panels of an inventory moisture-heat-protective coating.

    3.5. Geotextile, dornite, flax wool or other heat-insulating rolled materials can be used as heat-shielding materials.

    3.6. In addition to complex moisture and heat-protective technological equipment, the concreting site must be provided with:

    A concrete pump capable of continuously supplying the concrete mix with the required mobility into the formwork;

    Crane with sufficient outreach to supply materials during the construction of supports;

    Manual vibrators for concrete mix compaction;

    Bunker (bucket) for supplying, if necessary, concrete;

    A set of hand tools for leveling the concrete mix;

    A set of "carrier lamps" for visual control, if necessary, of the quality of reinforcing and formwork work, laying and compacting the concrete mixture;

    3.7. Warmhouses should be made of materials that have low blowability (rubberized fabric, polymer films, etc.) and do not become brittle in the cold.

    3.8. When installing greenhouses, it is necessary to ensure a hermetic adjoining of the coatings to the base and previously concreted concrete and reinforced concrete elements.

    3.9. To reduce the risk of cracking in the zone of contact of the hardening concrete with the hardened, the greenhouses should provide heating of the previously concreted structures.

    3.10. To ensure normal conditions for heat exchange, there should not be very narrow cavities in the greenhouse. The distance between the fence of the greenhouse and the heated structure must be at least 1.0 ... 1.5 m.

    3.11. In greenhouses with a height of more than 4.0 m, the temperature should be controlled at a height of 0.4 m from the floor and at the ceiling. If there is a temperature difference along the height of the greenhouse more than 5 - 7 ° C, it is necessary to equalize the air temperature with the help of fans, supplying heated air from the top of the greenhouse to the bottom.

    3.12. When using heat generators on liquid fuel, if necessary, ventilation of the greenhouses should be arranged.

    3.13. Teplyaks are equipped with liquid fuel heat generators or electric heaters. The number of heat generators should be determined by calculation, depending on the outdoor temperature, the required air temperature inside the greenhouse, the conditions for heat exchange between the greenhouse and the environment, and the design of the greenhouse enclosures.

    3.14. The greenhouse should be equipped with heat generators or electric heaters with adjustable power, which will subsequently allow them to smoothly regulate the air temperature in the greenhouse by turning them on or off.

    3.15. The greenhouse must have a rigid structure that can withstand the own weight of the fences, wind pressure, snowfall, etc.

    3.16. The greenhouse must be adequately lit to ensure normal working conditions when placing concrete and finishing the surface layer of concrete.

    3.17. In greenhouses, it is necessary to have a sufficient number of heat and moisture protective coatings for the care of concrete.

    Purpose of equipment or equipment

    Equipment or tooling

    Description, brand.

    Quantity (piece)

    Notes

    Concrete supply

    concrete pump truck

    "SHCVING" L str = 42 m

    Concrete compaction

    Deep vibrator, d = 50 mm, l = 35 cm.

    "Mennekes"

    Installation work

    Crane capacity 16 t

    KS-35715

    Concrete compaction

    Site vibrator

    VI-9-8

    2800 rpm

    Leveling and moving concrete

    Shovel shovel

    Smoothing the concrete surface

    wooden rule

    -

    4. Preparatory, formwork and reinforcing work

    4.1. Prior to the start of formwork and reinforcement work on the erection of concrete structures, geodetic marking work should be fully completed with fixing the axes of concrete structures in place. Particular attention should be paid to geodetic work when constructing formwork and installing reinforcing cages.

    4.2. In the course of work, special attention should be paid to ensuring the rigidity of the installed formwork and to the inadmissibility of its deformation and separation under the pressure of the column of the laid concrete mixture, as well as to determine the rate of erection of all support elements, taking into account the setting time of the concrete mixture.

    4.3. Prior to the start of reinforcement work, the base should be cleaned of debris and dirt.

    4.4. When preparing concrete bases and working joints to remove the cement film, surface treatment is carried out with a water and air jet, metal brushes or sandblasting installations.

    For reinforcement, reinforcement with a diameter of 32 mm, 22 mm, 20 mm, 16 mm, 14 mm, 12 mm class AIII, reinforcement steel grade 25G2S, reinforcement with a diameter of 10 mm, 8 mm class AI steel grade St5 sp. GOST 5781-82.

    The order of storage of reinforcement and angle.

    Steel reinforcement is stored in a specially designated area. Reinforcement packages are laid on wooden linings and covered with waterproof material. Rough handling of reinforcement, its fall from a height, exposure to shock loads, mechanical damage is not allowed.

    Inspection.

    Reinforcing bars should be checked for defects, such as cracks, local thinning, pores, peeling, dents, bends, rust, local or general distortions, deviations from the specified cut length of the bar.

    Armature cleanliness.

    By the time the reinforcement cage is assembled, the reinforcement must be clean, free of dirt, oil, grease, paint, rust, mill scale and similar materials.

    The fittings are connected into spatial frames using a knitting wire D = 1.6 mm. Reinforcing reinforcement is overlapped using a knitting wire, the overlap of reinforcement bars is at least 30 diameters of the reinforcement. No more than 50% of bar joints should be located in one section.

    4.7. Prior to the start of work on concreting structures, it is necessary to produce the required number of spacers-"crackers" that provide the required thickness of the protective layer and the design position of the reinforcing cages in all sections of the concreted structural elements. The quality of concrete spacers-"crackers" for the design of the protective layer of concrete should not be lower than the quality of concrete structures.

    It is allowed to use plastic spacers - "crackers" made in the factory.

    4.8. Distance pads should be made of fine-grained concrete with the inclusion of crushed stone screenings. The dimensions and configuration of concrete spacers-"crackers" must correspond to the design of the reinforcing cage and the design values ​​of the concrete protective layer, ensure their stable position in the formwork and on the reinforcing bars of the cage.

    To eliminate the possibility of staining and subsequent destruction of the surface layer of concrete at the locations of the “crackers” gaskets, the outer (supporting) surface of the gasket made of fine-grained concrete in contact with the formwork should have a curvilinear outline (radius of curvature 30 - 50 m).

    4.9. During the execution of reinforcing work, it is necessary to install embedded parts in accordance with the project.

    4.10. Preparation of reinforcing cages (separate items) and embedded parts, their installation and installation in the formwork and other work related to design features reinforcement of the concreted elements is performed in accordance with the working drawings.

    4.11. Reinforcing bars laid in the formwork of the frame elements are fixed with the required number of spacers - "crackers", reliably ensuring the design location of the reinforcing cage in the formwork and the size of the protective layer of concrete in all sections.

    4.12. Reinforcement installed in place with all embedded elements (parts) must be a rigid frame that cannot be upset during concreting.

    4.13. Plastic or metal tubes should be fixed to the reinforcing cages in the surface layer and in the central zones in order to form wells for measuring the temperature of the concrete during its curing.

    4.14. Formwork panels are installed in accordance with the project. For concreting, an inventory formwork made in accordance with TU is used. Additional sections of the formwork are made on site. For additional formwork, a wooden frame is used. It is necessary to ensure a good tightness of the mutual adjoining of the edges of the formwork panels. If leaks are found that can lead to leakage of cement mortar during concreting, all detected places should be securely sealed before applying lubricant by gluing with adhesive tape (construction plaster) 30 - 40 mm wide or smeared with sealant. The joints of formwork panels are sealed with silicone or other sealants. Formwork panels must be fastened and fixed (uprights, stops, braces, tie rods, etc.) in such a way as to create a rigid, geometrically unchanging structure.

    4.15. Before installation, the forming surfaces of the formwork panels should be wiped with burlap impregnated with grease or other grease. The lubricant should be applied in an extremely thin layer, which excludes the ingress of lubricant on the reinforcement during the installation of formwork panels.

    4.16. After an instrumental check of the position of the reinforcing cages, installed formwork panels, the reinforcing cages and the installed formwork are examined and an act is drawn up for covert work with the participation of representatives of the Customer, the general contractor and supervisory services.

    5. Concreting

    5.1 Before starting work on laying concrete, the equipment for concrete supply should be prepared for operation and its serviceability should be checked.

    5.2 Prior to the start of work, the site manager must clarify: the time of delivery of concrete from the plant to the facility, the availability of documentation confirming the compliance of the indicators of the concrete mix and concrete with the requirements of this "Technological map". A representative of the construction laboratory must check the availability of a standard cone for determining the mobility of the concrete mixture, thermometers for measuring the temperature of the concrete mixture and outside air, a device for determining the amount of entrained air in the concrete mixture and the sufficiency of molds for making control concrete cubes.

    5.3 An effective operational connection must be established between the concrete plant and the facility under construction, ensuring the delivery of the concrete mixture in full compliance with the requirements of the project and this "Technological map".

    5.4 Delivery of the concrete mixture to the construction site must be carried out by truck mixers. The number of truck mixers must be assigned from the conditions of the volume of concreted structural elements, the intensity of laying the concrete mixture, the distance of its delivery, the concrete setting time. The total time of delivery of the concrete mix to the construction site, its laying in structural elements should not exceed its setting time.

    5.5 Descent The supply of concrete mixture to the place of laying can be carried out through link, easily assembled disassembled trunks, concrete pipelines and the end hose of the concrete pump.

    5.6 Before supplying the concrete mixture directly into the body of the structure, the concrete pump must be tested by a test hydraulic pressure, the value of which.

    The assigned composition and mobility of the concrete mixture must be checked, refined on the basis of test pumping of the concrete mixture.

    The internal surfaces of the concrete pipeline before concreting must be moistened and lubricated with lime or cement mortar.

    5.7 During production concrete work it must be taken into account that in cases of interruptions in the pumping of the mixture from 20 to 60 minutes, it is necessary to pump the concrete mixture through the system every 10 minutes for 10 - 15 seconds. at low operating modes of the concrete pump. For breaks exceeding the specified time, the concrete pipeline must be emptied and flushed.

    5.8 The intensity of concreting should be determined by the construction laboratory, taking into account the properties of the concrete mixture, the distance of delivery of concrete.

    5.9 When performing work in the winter period, before concreting each element, the base and upper zone of the previously concreted elements should be warmed up to a temperature of at least plus 5 °C to a depth of at least 0.5 m.

    5.10 To prevent the appearance of thermal cracks in structures, the value of the heating temperatures of previously concreted elements is linked to the temperature of the incoming concrete mixture in accordance with the table.

    Table 1

    Reinforcement control

    Table 4

    Parameter value, mm

    Control (method, scope, type of registration)

    1. Deviation in the distance between separately installed working rods for:

    Technical inspection of all elements, work log

    columns and beams

    ± 10

    slabs and foundation walls

    ±20

    massive structures

    ± 30

    2. Deviation in the distance between the rows of reinforcement for:

    Same

    slabs and beams up to 1 m thick

    ± 10

    structures with a thickness of more than 1 m

    ±20

    3. Deviation from the design thickness of the protective layer of concrete should not exceed:

    with a protective layer thickness of up to 15 mm and linear dimensions of the cross-section of the structure, mm:

    up to 100

    from 101 to 200

    with a protective layer thickness of 16 to 20 mm incl. and linear dimensions of the cross-section of structures, mm:

    up to 100

    4; -3

    from 101 to 200

    8; -3

    from 201 to 300

    10; -3

    St. 300

    15; -5

    with a protective layer thickness of more than 20 mm and linear dimensions of the cross-section of structures, mm:

    up to 100

    4; -5

    from 101 to 200

    8; -5

    from 201 to 300

    10; -5

    St. 300

    15; -5

    All reinforcement installed in the formwork must be taken before concreting; the results of the survey and acceptance should be documented in an act for hidden work.

    The main operations that are subject to control in the production of reinforcing work, control methods and controlled operations are given in the table.

    Methods of control and controlled elements in the production of reinforcing work

    Table 5

    Rebar stock

    Assembly reinforcing mesh

    Composition of control

    Cleanliness, reinforcement quality, bar dimensions, steel grade

    Welds, dimensions, mesh placement, cover, quality

    Method and means of control

    Visual measuring, meter

    Visual measuring, steel meter

    Mode and scope of control

    Solid

    All grids

    The person in control

    Master

    Master, laboratory assistant

    The person responsible for organizing and exercising control

    foreman

    foreman

    Services involved in monitoring

    Laboratory

    Control results registration wizard

    Journal of General Works. Welding log

    7.13. The technological requirements that must be observed during the production of concrete work, and checked during operational control, as well as the scope, methods or methods of control, are given in the table.

    Production of concrete works.

    Table 6

    Control

    Method or method of control

    1. At the place of laying, the mobility of the concrete mixture should be in the range of 10 - 15 cm for structural elements

    At least twice per shift with rhythmic mass concrete placement, other concrete mixer trucks visually.

    Checking in accordance with GOST 10181.1-81 with registration in the log of concrete work, concrete care, the Act of manufacturing control samples, the log of the arrival of the concrete mixture.

    2. The temperature of the concrete mixture at the place of laying should not differ from the regulated one by more than ± 2 °C(from 5 to 25°)

    In every concrete mixer on the construction site

    Registration, measuring

    3. The thickness of the laid concrete layer should not exceed 40 cm

    Permanent, during concrete placement

    Measuring, visual

    4. The volume of air entrained in the concrete mixture is from 3 to 5% for concrete with frost resistance grade F 200

    Once per shift (with constant: concrete composition, quality of materials, concrete mix preparation modes)

    Checking in accordance with GOST 10181.3-81

    5. Norms of samples when concreting structures

    For each structural element monolithic concrete structures at least one series per shift.

    6. Number of series of samples made from one sample of concrete mix at the facility

    Registration

    7. Acceptance of structures for water tightness and frost resistance is carried out based on the requirements of project documentation

    According to the acts of the supplier plant, the results of determining the frost resistance of concrete laid in the constructive
    .

    According to the quality document according to GOST 7473-94 clauses 4.1 - 5.2 with the application of the factory test certificate according to GOST 10060 -95 and according to GOST 12730.5-84

    8. Labor protection in the course of work

    Labor protection is carried out in accordance with the health and safety plan (in accordance with SNiP 12-03-2001, SNiP 12-4-2002, PB 10-382-00).

    8.1. General requirements

    Persons who have reached the age of 18 and are recognized as fit for this work are allowed to work independently as a concrete worker. medical commission who have been trained in safe methods and techniques for the production of work and briefings on labor safety and who have a certificate for the right to work as a concrete worker.

    A concrete worker starting work must undergo an introductory briefing on labor safety, industrial sanitation, first aid, fire safety, environmental requirements, working conditions, initial briefing at the workplace, which should be recorded in the relevant journals with the obligatory signature of the instructed and instructing. Repeated briefing is carried out at least 1 time in 3 months. An unscheduled briefing is carried out when new or revised standards or other normative documents on labor protection, in case of a change in the technological process, replacement or modernization of equipment and tools, replacement of materials, in case of violation by employees of labor safety requirements, at the request of supervisory authorities, during breaks in work for more than 30 calendar days. Target briefing is carried out when performing one-time work.

    Prior to the start of work, workplaces and passages to them must be cleared of foreign objects, debris, dirt, and in winter - from snow and ice and sprinkled with sand.

    Be in a hazardous work area lifting mechanisms, and also it is forbidden to stand under the lifted load.

    Machines, power tools and lighting lamps can only be switched on with the help of knife switch starters. Do not allow the presence of poorly insulated electrical wires, unenclosed electrical devices on the site. When working with power tools, the concrete worker must be trained and have I qualification group on safety.

    Before starting the equipment, check the security of guards in all exposed rotating and moving parts.

    If a malfunction of the mechanisms and tools with which the concrete worker works, as well as fences, is detected, it is necessary to stop work and immediately inform the foreman.

    Upon receipt of the tool, you must make sure that it is in good condition; the faulty tool must be handed over for repair.

    When working with hand tools (scrapers, bush hammers, shovels, rammers), it is necessary to monitor the serviceability of the handles, the tightness of the nozzles on them, and also to ensure that the working surfaces of the tool are not knocked down, blunt, etc.

    An electrified tool, as well as the electrical wire that feeds it, must have reliable insulation. Upon receipt of the power tool, it is necessary to check the condition of the wire insulation by external inspection. When working with the tool, make sure that the power cord is not damaged.

    8.2. Requirements before and during work

    When starting work, the concrete worker should wear the overalls prescribed by the norms, while the hair should be removed under the headgear, cuffs fastened or tightened with an elastic band.

    When laying the concrete mixture with an autoconcrete pump, it is necessary to check the operation of a two-way signaling (sound, light) between the autoconcrete pump driver and the workers receiving the concrete. Clean and tightly lock all interlocks of the concrete pipeline. Do not accept concrete mix with a defective concrete pump. The driver of the truck-mounted concrete pump before starting must give a warning signal and start the concrete pump for testing at idle for 2-3 minutes.

    When delivering concrete in a concrete mixer truck, the following rules must be observed:

    When unloading the concrete pump into the bunker, you must first put the concrete mixer truck on the hand brake and give a sound signal;

    At the time of the approach of the concrete mixer truck, all workers should be on the side of the access road, opposite to the one on which the movement takes place;

    It is forbidden to approach the mixer truck until it has come to a complete stop.

    Before starting to place the concrete mixture in the formwork, it is necessary to check:

    Fastening formwork, supporting scaffolding and working decks;

    Fastening to the supports of the loading funnels, trays and trunks for lowering the concrete mix into the structure, as well as the reliability of fastening the individual links of the metal trunks to each other;

    The condition of the protective hoods or flooring around the feed funnels.

    Concrete workers working with vibrators are required to undergo a medical examination every 6 months.

    Women are not allowed to work with a manual vibrator.

    Concrete workers working with electrified tools must know the measures to protect against electric shock and be able to provide first aid to the victim.

    Before starting work, it is necessary to carefully check the serviceability of the vibrator and make sure that:

    The hose is well attached, and if it is accidentally pulled, the ends of the winding will not break;

    The supply cable has no breaks and bare spots;

    The ground contact is not damaged;

    The switch is working properly;

    The bolts that ensure the tightness of the casing are well tightened;

    The connections of the parts of the vibrator are quite tight, and the motor winding is well protected from moisture;

    The shock absorber on the vibrator handle is in good condition, and adjusted so that the vibration amplitude of the handle does not exceed the standards for this tool.

    Before starting work, the body of the electric vibrator must be grounded. The general serviceability of the electric vibrator is checked by trial operation in a suspended state for 1 minute, while the tip must not be rested on a solid base.

    To power the electric vibrators (from the switchboard), four-wire hose wires or wires enclosed in a rubber tube should be used; the fourth core is necessary for grounding the vibrator case, operating at a voltage of 127 V or 220 V.

    You can turn on the electric vibrator only with a knife switch protected by a casing or placed in a box. If the box is metal, it must be grounded.

    Hose wires must be suspended and not run over the laid concrete.

    Do not drag the vibrator by the hose wire or cable when moving it.

    In the event of a break in live wires, sparking of contacts and a malfunction of the electric vibrator, stop work and immediately inform the master.

    Work with vibrators on ladders, as well as on unstable scaffolds, decks, formwork, etc. prohibited.

    When working with electric vibrators operating from a mains voltage of up to 220 V and above, it is necessary to wear rubber dielectric gloves and boots.

    During continuous operation, the vibrator must be turned off every half hour for five minutes to cool down.

    When it rains, the vibrators should be covered with a tarpaulin or kept indoors.

    During breaks in work, as well as when concrete workers move from one place to another, the vibrators must be turned off.

    The concrete worker working with the vibrator must not allow water to come into contact with the vibrator.

    8.3. Safety precautions when working at height.

    Perform all work in accordance with SNiP 12-03-2001 "Labor safety in construction" part 1, "Labor safety in construction" part 2.

    Workplaces and passages to them at a height of 1.3 m or more, and at a distance of less than 2 m from the boundary of the difference in height, are protected by temporary inventory fences in accordance with GOST 12.4.059-89. If it is impossible to use safety fences or in the case of a short period of workers being at height, it is allowed to perform work using a safety belt.

    Scaffolds are equipped with ladders or ladders for lifting and lowering people in the amount of at least two.

    Ladders and ladders are equipped with a device that prevents the possibility of shifting and overturning them during operation.

    Employees involved in the assembly and disassembly of scaffolding must be instructed on the methods and sequence of work and safety measures.

    Metal scaffolding is not allowed to be installed closer than 5 m from the masts of the electrical network and operating equipment. Electric wires, located closer than 5 m from the scaffolding, must be de-energized and grounded, or enclosed in boxes, or dismantled during their installation or disassembly. Scaffolds must be grounded.

    Access for unauthorized persons (not directly involved in these works) to the area where the scaffolds are installed or dismantled must be closed.

    During work at height, the passage under the work site must be closed, and the danger zone is fenced off and marked with safety signs. Scaffolding should not be used for storing materials.

    Only those materials that are directly used (recycled) are fed to the scaffolding.

    9. Environmental protection

    9.1. The CONTRACTOR-PERFORMER of WORKS shall keep the construction site clean and provide appropriate facilities for the temporary storage of all types of waste until they are removed. Construction waste is stored only in specially designated areas indicated on the construction plan.

    The CONTRACTOR-PERFORMER is responsible for ensuring the safe transport and disposal of all types of waste in such a way that it does not lead to environmental pollution or damage to human or animal health.

    All sites and buildings are kept clean and tidy. All working personnel were instructed against signature, entered in the relevant journal and informed about the requirements for the maintenance of the workplace and the responsibility of each for the order at their place of work and rest.

    Waste disposal should include the following:

    Separate containers for different types of waste (metals, food waste, hazardous materials, garbage, etc.) with tight-fitting lids;

    Locations for containers;

    Waste scrap metal is temporarily stored at designated landfills agreed with the Committee for Environmental Protection, the Land Committee, local authorities;

    Concrete waste is temporarily stored at temporary waste storage sites in specially equipped areas with improved coverage. Waste of reinforced concrete structures will be taken out by special vehicles for disposal at the landfill;

    Washing of truck mixers and concrete pumps should be carried out only in the places indicated by the General Contractor.

    Lumpy wood waste, unsuitable for use at the site, is temporarily stored at the temporary storage site and will be transported by road to be placed at the landfill;

    Household waste will be removed by special vehicles for disposal and processing at the landfill in accordance with the waste removal agreement with a specialized company.

    All waste hazardous to health undergoes final disposal at the relevant enterprises or landfills agreed with the local administration and regulatory authorities, under contracts, copies of which will be submitted to the Customer.

    Refueling of construction equipment in the process of work is carried out by certified tankers “from the wheels”. All oils and lubricants are stored in warehouses in hermetically sealed containers with clear markings in Russian. If fuel and lubricants get on the soil or concrete surface, measures are immediately taken to cut off and dispose of contaminated soil, with concrete surface Fuel and lubricants are removed with sand or sawdust with subsequent disposal.

    9.2. Protection of flora, fauna and habitat.

    The planned activity sets the goal of minimal and temporary alienation of land, disturbance of vegetation cover.

    In order to minimize the negative impact on the flora and fauna, during the construction of the facility, the CONTRACTOR-PERFORMER of WORKS must carry out organizational and technical measures:

    Providing the facility with individual, passive and active fire fighting equipment, strict control over compliance with fire safety rules;

    Preservation of the soil cover by maintaining equipment in good condition, eliminating the spill of oil products on the soil;

    Operation of machinery only within the boundaries of the allotment of the construction site using existing access roads;

    During the construction period, the protection of the wildlife, first of all, will be in compliance with environmental legislation, minimizing the impact on the atmospheric air, surface water, which will indirectly reduce the impact of the facility on the environment.

    9.3. Minimization of air pollution and noise pollution of the environment.

    Reducing the dust content of the air that occurs during construction is achieved due to the following:

    The use of crushed stone pavement of roads, both at the construction site and between the construction site and the settlement for the construction workers, as well as within the settlement;

    Regular cleaning of roads and wetting them to prevent dust in the air.

    To reduce possible negative impacts to atmospheric air during construction, the CONTRACTOR-PERFORMER of WORKS should use only serviceable construction equipment with adjusted fuel equipment that ensures the lowest possible emission of pollutants into the environment, including effective noise suppressors;

    Operates and maintains machinery in accordance with manufacturers' instructions and instructions, with particular attention to controlling noise and pollutant emissions;

    Provides continuous monitoring of compliance current rules operation;

    The equipment used for construction is subject to regular maintenance and checks for possible malfunctions;

    It is not allowed to burn production waste;

    It is forbidden to use ozone-depleting agents and freons in cooling and fire extinguishing systems;

    During the summer period of construction, in order to reduce dust on access or working roads, it is necessary to continuously water the surface of the roadbed with water using watering machines.

    9.4. Plan CONTRACTOR-PERFORMERon the organization of work on the collection, storage and disposal of waste

    During the production of works at the facility, 2 types of waste are generated:

    Industrial (construction waste);

    Household waste.

    When handling hazardous waste, an appropriate act is drawn up based on the results of bringing the products to a safe state, which is approved by the head of the enterprise - the owner of the product.

    In the process of collecting and accumulating waste, they are identified with the determination of whether they belong to a certain type of waste; separate containers are provided for each type of waste closed type(metals, food waste, hazardous materials, garbage, etc.), marked with warning signs.

    CONTRACTOR-PERFORMER develops measures to minimize the amount of waste generated:

    Use of equipment and spare parts for the full expected period of their operation;

    Use of waste as a raw material in a new technological cycle;

    Shift foremen are responsible for compliance with environmental protection requirements.

    Bibliography

    GOST 2379-85 GOST 10060.0-95


    TYPICAL TECHNOLOGICAL CHART (TTK)

    APPLICATION OF CONCRETE WITH ANTI-FROST ADDITIVES

    1 area of ​​use

    1.1. The technological map has been developed for concreting structures in winter conditions with the use of antifreeze additives.

    1.2. Winter conditions are conditions under which the average daily outdoor temperature is below 5°C and the minimum daily temperature is below 0°C.

    1.3. The essence of the method of introducing antifreeze additives into the concrete mixture consists in introducing into the concrete mixture during its manufacture additives that lower the freezing point of water, ensure the hydration reaction of cement and its delayed hardening at low temperatures.

    1.4. Antifreeze additives are used in the case of a device during the construction in winter conditions of monolithic concrete and reinforced concrete structures, monolithic parts of prefabricated monolithic structures, monolithic joints of prefabricated structures.

    1.5. The scope of works considered by the technological map includes:

    Laying of concrete mix with antifreeze additives;

    1.6. Concreting in winter conditions with the use of antifreeze additives is carried out in accordance with the requirements of federal and departmental regulations, including:

    SNiP 3.03.01-87. Bearing and enclosing structures;

    SNiP 12-03-2001. Labor safety in construction. Part 1. General requirements;

    SNiP 12-04-2002. Labor safety in construction. Part 2. Construction production.

    - "Guidelines for the production of concrete work in winter conditions, areas Far East, Siberia and the Far North". Moscow, Stroyizdat, 1982;

    - "Manual for the production of concrete work." Moscow, Stroyizdat, 1975;

    - “Guidelines for quality control of construction and installation works”, St. Petersburg, 1998.

    2. Organization and technology of work performance

    2.1. Prior to the start of the installation of a robot for the use of concrete mixtures with antifreeze additives in winter conditions, it is necessary:

    Execute and accept the underlying structures;

    Prepare tools, fixtures, inventory;

    Deliver to workplace materials and products,

    Instruct workers on labor protection;

    Familiarize the performers with the technology and organization of work.

    2.2. The use of concrete mixtures with antifreeze additives includes:

    Selection of antifreeze additives;

    Preparation of concrete mix with antifreeze additives;

    Transportation of concrete mix with antifreeze additives;

    Laying concrete mix with antifreeze additives;

    Curing of concrete with antifreeze additives;

    Quality control and acceptance of works.

    2.3. As antifreeze additives, it is possible to use chemicals, the characteristics of which are given in Table. 2.1. It is recommended to use complex additives containing compatible plasticizing and antifreeze (simultaneously accelerating hardening) components.

    2.4. The scope of concrete with antifreeze additives and hardening accelerators are given in table. 2.2.

    2.5. The antifreeze additives listed above have a different mechanism of influence on the process of concrete structure formation. Some of them only reduce the freezing point of water and do not affect the rate of setting and hardening of concrete (for example, HH, M).

    Other additives, along with effective antifreeze properties, are simultaneously setting accelerators (P) and hardening accelerators (NK, NNK). Approximate strength of concrete with antifreeze additives is given in Table 2.3.

    2.6. The optimal amount of antifreeze additive depends on the minimum temperature of the concrete mixture. When curing concrete with antifreeze additives, it is necessary to create such conditions that during the period of transportation and laying the concrete mixture does not cool below 0°C. In this case, the optimal amount of antifreeze additives should correspond to the data in Table. 2.4.

    2.7. Concrete mixtures with NK, NNKi, especially P additives are characterized by accelerated setting times, which makes it difficult to lay the concrete mixture and degrades the structure. cement stone. Therefore, simultaneously with the indicated antifreeze components, it is recommended to introduce plasticizing agents into the composition of the concrete mixture. As a plasticizing component of the complex additive, which increases the mobility and reduces the water demand of the concrete mixture, it is recommended to use the additives given in Table. 2.5.

    Concrete with the addition of potash during setting and initial hardening must have negative temperature.

    2.6. The most effective complex additives are compositions that include surface-active substances (surfactants) and electrolytes. With properly selected dosages of electrolyte and surfactant additives, it is possible to use the plasticizing properties of the latter and at the same time obtain a high hardening rate. The list of the most effective complex antifreeze additives and their reduced amount is given in Table. 2.5.

    2.7. The recommended amount of chemical additives for complex curing of concrete is given in Table 2.6. The use of concrete with antifreeze additives should be preceded by laboratory tests of the effect of additives on the strength and hardening rate of concrete.

    2.8. The final choice of the type of chemical additives is made taking into account the prices of manufacturers and suppliers of chemical additives.

    2.9. The preparation of the concrete mixture is organized at a concrete plant. The selection of the concrete composition for winter laying is carried out in accordance with GOST 27006-86. The selection of the composition is carried out by a calculation-experimental method, which includes the solution of the following issues:

    Determination of all requirements for the quality of the concrete mix and concrete;

    Quality assessment and selection of materials for the preparation of concrete mix;

    Calculation of the nominal composition of concrete;

    Experimental verification of the design composition;

    Adjustment of the composition and calculation of the production composition of concrete.

    2.10. When preparing a concrete mixture, it is possible to heat the mixing water, warm or heat the components, as well as heat the concrete mixing unit, batching and bunker compartments.

    2.11. To obtain the maximum temperature of the concrete mixture at the outlet of the concrete mixer, water is heated up to the maximum possible temperature of + 80 ° C.

    2.12. The mixing time of the concrete mixture in the concrete mixer should be 25% longer than in summer conditions, and not less than the values ​​given in Table 2.7.

    2.13. The amount of chemical additives established in accordance with the recommendations is introduced during the preparation of concrete mixtures in the form of aqueous solutions of a working concentration. Salt solutions are prepared on water heated to 40 ° C in mixers. The main indicators of aqueous solutions of antifreeze and plasticizing additives are given in table. 2.8, table 2.9.

    2.15. Transportation of the prepared concrete mix is ​​carried out by truck mixers. To minimize heat loss, the open parts of the mixer truck drum are covered with moisture-proof materials and insulated. The neck of the mixer truck drum is insulated and covered with a heat-insulating cover or the neck is heated with exhaust gases from the engine. When using only potash, it is recommended to add it at the facility by introducing an aqueous solution of potash with mixing of all components in the mixer truck drum. protected from wind and precipitation. The bunker for supplying the concrete mixture must also be insulated.

    2.16. When using concrete pumping plants to supply the concrete mixture, all components and parts in contact with the concrete mixture are insulated. At the same time, the pipelines and the main components of the concrete pump should be especially carefully insulated in order to maintain the initial temperature of the concrete. At extreme temperatures down to -40°C, in addition to the insulation of the main components of the concrete pump, additional heating of the insulated concrete pipeline is required with flexible heating elements. It should also provide for hot water in insulated tanks for flushing concrete pipelines after concreting.

    2.17. Maintaining monolithic concrete and reinforced concrete structures erected from concrete with antifreeze additives is carried out in compliance with the following guidelines:

    Concrete surfaces that are not protected by formwork, in order to avoid moisture loss or increased moisture due to precipitation, should be immediately covered with a layer after concreting. waterproofing material(polyethylene film, rubberized fabric, roofing material, etc.);

    Concrete surfaces that are not intended in the future for a monolithic connection with concrete or mortar can be coated with film-forming compounds or protective films (bitumen-ethinol, etinol varnish, etc.);

    In the event of an unexpected decrease in the temperature of concrete below the design structure, it is necessary to insulate or heat it until the concrete reaches critical strength.

    2.18. Demoulding of load-bearing concrete and reinforced concrete structures should be carried out after the concrete reaches the strength given in Table. 2.9.

    2.31. If it is impossible to provide the required strength of concrete by the time the structure is loaded with a standard load, it is allowed, with an appropriate feasibility study, to use a concrete class increased by one step.

    2.32. It is allowed to remove the formwork, which perceives the mass of concrete of structures reinforced with load-bearing welded frames, as well as side elements that do not bear the load from the mass of structures, after the concrete reaches critical strength.

    2.33. The strength of concrete before stripping must be confirmed by tests.

    2.34. Removal of thermal protection and formwork from structures, when using concrete with antifreeze additives - upon reaching the strength specified in section 3.

    3. Requirements for the quality and acceptance of work

    3.1. When curing concrete with antifreeze additives in winter conditions, production control quality which includes:

    Input control of materials for the preparation of concrete mix, reinforcement and embedded parts, thermal insulation materials;

    Operational control of the performance of reinforced concrete works;

    Acceptance control of work performed.

    At all stages of work, inspection control is carried out by representatives of the technical supervision of the customer.

    3.2. Input quality control of materials, semi-finished products, products and parts consists in checking external inspection their compliance with GOSTs, TUs, project requirements, passports, certificates confirming the quality of their manufacture, completeness and compliance with their working drawings. During the input control, compliance with the rules for unloading and storage is also checked. Input control is performed by line personnel when materials, structures, products arrive at the construction site.

    3.3. Operational control should be carried out during the performance of reinforced concrete work and ensure the timely detection of defects and the adoption of measures to eliminate and prevent them. During operational control, they check the compliance of the work performed with the working project and regulatory requirements. The main tasks of operational control:

    Compliance with the technology of performing reinforced concrete works;

    Ensuring compliance of the work performed with the project and the requirements of regulatory documents;

    Timely detection of defects, their causes and taking measures to eliminate them;

    Performing subsequent operations after the elimination of all defects made in previous processes;

    Increasing the responsibility of direct executors for the quality of their work.

    3.4. When laying the concrete mixture, it is necessary to control:

    The quality of the concrete mixture;

    Rules for unloading and distribution of concrete mix;

    The temperature of the concrete mixture;

    Concrete compaction mode;

    The order of concreting and ensuring the solidity of the structure;

    Timeliness and correctness of sampling for the manufacture of control samples of concrete.

    3.4. When laying and compacting a concrete mixture with antifreeze additives, laid in winter conditions, the requirements given in Table. 3.1.

    3.5. When curing concrete with antifreeze additives, the following is controlled:

    Maintenance of temperature and humidity conditions;

    Protection of hardening concrete from mechanical damage;

    curing time of concrete.

    3.6. Technical requirements when curing concrete with antifreeze additives are given in table. 3.2.

    3.6. Concrete quality control provides for checking the compliance of the actual compressive strength of concrete in the design with the design and specified in the terms of the intermediate control. The compressive strength of concrete should be checked by testing control cubes with dimensions of 100x100x100 mm in accordance with GOST 10180-90. Test specimens are made from samples of the applied concrete mix. Samples are taken at the place of preparation of the concrete mixture and directly at the place of concreting.

    At least two samples should be taken at the concreting site. From each sample, one series of control samples is made (at least three samples in a series). Control samples are concreted in detachable steel molds corresponding to GOST 22685-89. Before concreting, the inner surfaces of the molds are lubricated. The concrete mixture is placed in the molds immediately after sampling with compaction by bayoneting or vibrating. Control samples are stored under the conditions of hardening of the concrete structure. Demoulding the samples after keeping the structure.

    The terms for testing control samples are assigned by the construction laboratory, taking into account the achievement of design strength by the time of testing. Samples stored in frost must be kept for 2 ... 4 hours at a temperature of 15 ... 20 degrees C before testing. Intermediate control is carried out after the temperature has dropped to the calculated final temperature.

    3.7. When accepting a sustained design, check:

    Compliance of the design with working drawings;

    Conformity of concrete quality to the project;

    The quality of the materials used in the construction, semi-finished products and products.

    3.8. The requirements for the finished design are given in Table. 3.3.

    ...
    Loading...
    Top